From the Inside

Progress at Verto has moved indoors as the installation of kitchens and bathrooms commence on the Ground and First Levels turning these empty spaces into homes.

Internal doors have been installed on all levels as well as all plasterboard wall linings. Window installation to Level Four has been completed with the curtain wall system, an outer covering of the building, currently underway.

Level Four ceilings have been installed while tiling is underway for the kitchen, bathrooms and entrance ways on the Ground and First Level as seen in the images gallery.

On the outside of the building painting still continues while the waterproof membrane for the roof is 100% complete.

Ancillary structures such as the Valve Room and Rubbish Enclosure are progressing well with in ground drainage now complete.

99% of the balcony handrails are now complete and installation of breezeway handrails have commenced with screens closely following.

On the Ground Level, apartments with studies have had their slider doors installed on a 3 track system allowing for different variations of the doors being opened as seen in the image gallery

The final fix of services such as electrical, plumbing, fire sprinkler and extraction ducting has commenced on the Ground Level with painting of the interiors now reaching Level Two.

Construction is progressing well and we continue to be on schedule for our settlement date, first quarter 2017.